Progress to date Page 6
16/04/09
The Hydro parts have been shipped from Germany, and have arrived in Brisbane as of the 28th May. They are being delivered by truck to the park and are due for arrival mid June.
Concreting work has begun in the building to reinforce the walls, and Tilman Heidemann (Heidemann Hydro) has arrived with a co-worker to ready the site for the installation.